Call KAP Décor · 437-217-0488
KAP Décor guide

Do you need a permit to renovate in Toronto?

You need a City of Toronto building permit for any renovation that changes structure, adds or moves plumbing, alters walls, or creates a new bathroom or dwelling unit. Cosmetic work, painting, flooring, cabinet replacement and like-for-like fixture swaps do not need one. A basement finish or a whole-home renovation almost always does, and KAP Décor prepares the drawings and pulls the permit as part of the project.

By KAP Décor Ltd. · Updated 15 September 2026

Permit needed by project

Timelines and fees are 2026 City of Toronto guidance and vary with scope. Confirm current numbers on toronto.ca building permits.

ProjectPermit?Typical review timeTypical fee
Painting, flooring, trim, new cabinets (same layout)Non/an/a
Kitchen renovation, like-for-like (no walls or plumbing moved)No (ESA notice for electrical)n/an/a
Bathroom renovation, fixtures moved / drain or vent alteredYes (plumbing)2-4 weeks$200-$500
Removing a non-load-bearing wallSometimes2-4 weeks$200-$500
Removing a load-bearing wall (beam)Yes (+ engineer)3-6 weeks$400-$900
Finishing a basementYes3-6 weeks$800-$1,800
Legal secondary suite (basement apartment)Yes6-12 weeks$1,500-$3,500
New deck over ~24 in / 60 cm above gradeYes2-5 weeks$200-$600
Rear, side or second-storey additionYes (+ zoning, often Committee of Adjustment)3-9 months$2,500-$8,000+
Electrical work beyond like-for-likeESA notification / permitvariesESA fee

What happens if you skip the permit

  • Work orders and stop-work orders. The City can order unpermitted work opened up for inspection or removed.
  • Insurance. An insurer can deny a claim for damage tied to unpermitted structural, electrical or plumbing work.
  • Resale. Unpermitted additions and suites show up in a home inspection, a Status Certificate or a lawyer's search, and buyers discount or walk.
  • Retroactive permits. Legalizing after the fact means opening finished walls for inspection, and sometimes redoing work that no longer meets code.

Who pulls the permit

The homeowner is the applicant of record, but a contractor almost always prepares and submits the application. KAP Décor produces the drawings, submits to the City, books the inspections at each stage (framing, plumbing, insulation, final), and does not close a project until the permit is signed off.

Renovation permit questions

Do I need a permit to renovate a bathroom in Toronto?

Only if you move fixtures, or alter the drain or vent. A like-for-like refit in the same layout does not need a building permit. Adding a bathroom, including in a basement, does.

Do I need a permit for a kitchen renovation in Toronto?

Not for a like-for-like renovation that keeps the layout. You do need one if you remove or alter a wall, move plumbing, or add fixtures. Electrical work requires an ESA notification either way.

How long does a building permit take in Toronto?

Simple interior permits are often 2-4 weeks; a basement finish is 3-6 weeks; a legal suite is 6-12 weeks; an addition that needs zoning relief can take 3-9 months.

Do I need a permit to finish my basement?

Yes. Basement finishing in Toronto requires a building permit for framing, insulation, electrical and any plumbing.

We handle the permit

KAP Décor prepares the drawings, submits to the City, and books every inspection. Book a free consultation.